Rock fall floods Tarbela tunnel 5, workers evacuated unhurt
WAPDA says the intake pit is drained and pumping continues at the unfinished powerhouse, while Haripur's deputy commissioner orders an inquiry into the breach.

HARIPUR: Water broke into Tunnel No. 5 at the Tarbela Dam's fifth extension hydropower project on Monday morning after a weak section of rock gave way, prompting the evacuation of Pakistani and foreign workers. WAPDA and Haripur police said no one was killed.
Haripur Deputy Superintendent of Police Masood Khan told Independent Urdu that work was going on inside Tunnel No. 5 with a body of water stored behind it. A barrier gave way on Monday morning and water rushed into the tunnel, he said. All Pakistani and foreign employees inside were moved to a safe place with police help.
WAPDA's spokesman gave a more specific cause: a weak section of rock fell during excavation of the second bench of the project's connecting tunnel, letting water from the intake pit into the tunnel and the powerhouse. He rejected reports that Tunnel No. 5 had collapsed and said the main tunnel, the powerhouse under construction, the tail race culvert and the switchyard were undamaged.
The intake pit has been fully drained, the spokesman said, and pumping has begun at the unfinished powerhouse. No more water is entering worksites downstream, he said. Senior WAPDA officers, the project's consultants and the contractor are at the site reviewing the situation.
Haripur Deputy Commissioner Waseem Ahmed went to the site with rescue and administrative teams and confirmed that the protective barrier had broken. According to Aaj News, he said a Pakistani worker was carried off by the fast flow and was rescued by emergency teams, and that no loss of life had been reported. He said a high-level inquiry committee will determine whether the breach came from a structural weakness or a technical fault, and that the next step will be decided after its report.
Aaj News also reported that all construction work on the project has been suspended indefinitely.
Haripur police said a final report on damage to infrastructure has not yet been compiled.
The fifth extension is built on Tunnel No. 5 and adds 1,530 MW through three units of 510 MW, raising the dam's installed capacity from 4,888 MW to 6,418 MW, according to the Ministry of Energy. Independent Urdu put the project's funding at about Rs82 billion from the World Bank's International Bank for Reconstruction and Development, with civil works contracted to Power China and completion first targeted for 2024.
Aaj News reported the approved cost at $807 million, with $390 million from the World Bank and $300 million from the Asian Infrastructure Investment Bank, and a $354.6 million civil works contract awarded in May 2021 to Power Construction Corporation of China Ltd. It said the completion date has been pushed to September 2027, that a Senate standing committee was told in September 2024 that securing an IRSA no-objection certificate to close Tunnel No. 5 had caused delay, and that work was stopped temporarily in August 2025 when the dam's water level rose.
How the reports differ
Independent Urdu led with Haripur police and WAPDA's spokesman, and reported no injury or loss of life. Aaj News led with Deputy Commissioner Waseem Ahmed's visit to the site, and alone reported that one Pakistani worker was swept away by the water and rescued, and that all construction work has been suspended indefinitely; Independent Urdu did not mention a suspension. The two gave different project figures: Independent Urdu put the funding at about Rs82 billion from the World Bank's IBRD with a 2024 completion target, while Aaj News reported an approved cost of $807 million with World Bank and AIIB contributions and a completion date pushed to September 2027. Both carried WAPDA's denial that Tunnel No. 5 had collapsed.

Tarbela T-5 construction halted indefinitely after bund breach floods tunnel
Deputy Commissioner Waseem Ahmed says all Pakistani and foreign workers were moved to safety and no one was killed; an inquiry will establish why the bund failed.
Minister Wattoo and Wapda chief tour Diamer-Basha and Dasu sites
Business Recorder's report carried no revised timeline, cost statement or progress figures from the visit to the two hydropower projects.

South Air starts direct Lahore-Peshawar flights
Four flights a week at first, with a flying time of 50 minutes to an hour, the airline says; a meeting in Islamabad also looked at routes to Gilgit, Skardu and Chilas.

Peshawar police identify four suspects in NADRA official's killing
CCTV footage traced the men's arrival at the scene, their movement in the area and the route they took afterwards, police sources say.

Constable killed, three policemen abducted in Hangu post attack
DPO Salahuddin Kundi says the attackers took the three personnel towards Khanano Kot in the Samana range after the raid on the Shalmas Pir Ziarat post.

Kundi rules out talks with armed groups, backs intelligence operations
Khyber Pakhtunkhwa's governor says Islamabad sets the province's security policy as Peshawar presses for Rs160 billion and officials report 3,788 militants killed in three years.

SIFC delegation in Peshawar pushes business reform, SEZ upgrades
The council's director general and secretary met Khyber Pakhtunkhwa's chief secretary and the city's chambers of commerce to review the Asaan Karobar Act rollout and three industrial zones.

Malakand jirga hears taxes will wait for lasting peace
Federal minister Amir Muqam told a Mingora gathering that no new levies would be imposed in Malakand Division until peace returns, as the KP police chief proposed a three-to-four-fold rise in martyr compensation.